Aurelia Metals secures final approval for Peak processing plant expansion
Bitget2026/10/28 01:44- Aurelia Metals received final regulatory approval to expand Peak Processing Plant operations, according to its October 28, 2026 quarterly update.
- Expansion projects are progressing toward raising annual processing capacity from 800,000 metric tons to 1,100,000–1,200,000 metric tons.
- Great Cobar completed 506 meters of mine development in the September quarter, bringing total development to 2,380 meters.
- The Great Cobar project remained on schedule and within its capital budget.
- FY27 production, cost and capital guidance was reaffirmed.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Texas Governor-Elect: Data centers must be suspended until measures to protect the interests of the people are introduced
The newly elected governor of Texas, Hinojosa, publicly stated that she despises the way data centers "take advantage of Texans" and that any measures must be paused before the introduction of new data centers. She also expressed willingness to collaborate with tech giants such as Elon Musk but emphasized that "it must be on our terms." Goldman Sachs previously warned that the current "blue wave" could result in a suspension order affecting the expansion capacity of approximately 45% of data centers across the United States, with Texas accounting for about 25%. Other states are also rushing to follow Texas' lead.

DIFC Court proposes establishing an oracle to enforce tokenized asset court rulings