Spanish Mountain Gold signs BC Hydro study agreement for 60 MW mine grid connection
Bitget2026/10/27 11:30- Spanish Mountain Gold signed a facilities study agreement with BC Hydro for grid connection of its British Columbia mining project.
- The 60 MW connection requires a new 230 kV switching station near BC Hydro's McLeese Lake Capacitor Station.
- Study completion is targeted for the second half of 2027; station operations are targeted for the first half of 2030.
- The study will provide capital cost estimates accurate to ±15%, supporting a construction decision.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
BUZZ-Cloudflare shares rise as Q3 revenue beats expectations

Terranor Group schedules Q3 results presentation
WTI crude oil futures prices fall by more than 1%

Yen appreciation and global bond slump lead Japan GPIF to first loss in six quarters, with almost no asset allocation adjustment
According to the latest quarterly report from Japan’s Government Pension Investment Fund (GPIF), its asset allocation remained almost unchanged from its model portfolio for the three months ending in late September. However, the fund recorded a 1.7% quarterly loss during this period—the first loss in six quarters—due to a global slump in bond prices and the appreciation of the yen.