Osisko Gold's Cariboo project reaches 28% completion
Bitget2026/10/27 11:04- Osisko Gold's Cariboo project remains on schedule for first gold in Q1 2029, with commercial production in H2 2029.
- Construction was approximately 28% complete as of September 30, 2026, based on cumulative costs of CAD 355 million.
- Estimated remaining construction costs total approximately CAD 907 million, net of leases and estimated pre-production revenue.
- Detailed engineering is approximately 42% complete, with more than 50% of procurement packages awarded.
- Underground development is expected to reach 360 meters monthly by year-end 2026, down from 500 meters previously, reflecting slower Valley portal excavation.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Europe’s largest asset manager Amundi tokenizes equity index fund on Ethereum

Apple plans to raise 7 billions USD to repurchase stocks, returning to the US dollar bond market after a year and a half.
Apple raised approximately $7 billion through this bond issuance, which is divided into seven tranches with maturities ranging from two to ten years. The longest tranche was initially priced at a spread of 80 basis points over US Treasuries. The proceeds from the bonds will be used for general corporate purposes, including stock buybacks, dividend payments, and capital expenditures. Analysts pointed out that shareholder returns are a higher priority than AI capital expenditures in Apple's capital allocation.