Cloudberry's Odal wind farm resumes normal operations after turbine repairs
Bitget2026/10/27 07:02- Cloudberry Clean Energy’s Odal wind farm is operating normally following production disruptions; all turbines met return-to-service criteria in Q2 2025.
- All material repairs are complete; Siemens Gamesa covered blade and other relevant component replacements under the existing service agreement.
- Odal Vind signed a 10-year support agreement with Siemens Gamesa, starting when the original five-year service agreement expires in 2028.
- The parties reached a final settlement covering outstanding project claims and the remaining construction payment obligation.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
South Korea’s current account surplus in September exceeded 60 billions USD for the first time, with semiconductor exports becoming the main driver
Driven by booming semiconductor exports, South Korea's current account surplus in September surged to a record high.

CoreWeave (CRWV.US) bonds hit a new low as changes in Texas data center policies impact AI cloud trading
CoreWeave (CRWV.US) bonds fell sharply on Wednesday, with some dropping to new lows.

AstraZeneca (AZN.US) reportedly receives a $10 billion acquisition offer! Shares of obesity drug developer Rhythm (RYTM.US) soar in response
According to three people familiar with the matter, AstraZeneca previously proposed to acquire obesity drug developer Rhythm Pharmaceuticals for approximately 10 billion dollars.
Goldman Sachs and Apollo in Talks to Sell 40 Billion-Dollar AI Chip Financing for SpaceX (SPCX.US), Market's Willingness to Take Over Faces Test
Goldman Sachs (GS.US) and Apollo Global Management (APO.US) are in talks with Wall Street investors to begin selling portions of a roughly $40 billion chip financing deal for SpaceX (SPCX.US).