Tiernan Gold targets H1 2027 Volcan project pre-feasibility study as environmental baseline work begins
Bitget2026/10/14 10:31- Tiernan Gold began a four-season environmental baseline program for its Volcan gold project in Chile’s Maricunga belt.
- Pre-feasibility study now targeted for H1 2027, with an updated mineral resource estimate planned alongside the study.
- Environmental Impact Assessment submission to Chile’s SEIA targeted for H2 2027.
- Project water supply base case remains continental groundwater from company-owned wells, with permitted maximum extraction of 170 liters per second.
- Tiernan reported cash of USD 36.2 million as of June 30, 2026 to fund the work program.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Anthropic spends $3.4 billion to purchase gas-fired power equipment to supply electricity for data centers
In September, Anthropic directly acquired Caterpillar equipment orders worth 3.4 billion USD, securing 1.7 GW of gas generator units, marking the largest single purchase of power generation equipment in AI history. This move bypassed utility middlemen, capturing scarce capacity at prices set years ago with near-term delivery. It is part of Anthropic's plan to invest over 895 billion USD in computing infrastructure by 2045.

Why Nintendo Stock Is One to Watch Ahead of the Holiday Season

A wallet address sold 1.44 million TRX via SunSwap in exchange for 460,000 USDT.

Data: Whales have cumulatively withdrawn approximately 13.4 million USDT from a certain exchange.