Nordic Mining Q3 rutile production jumps 74% to 2,190 tonnes
Bitget2026/10/11 20:00- Nordic Mining posted Q3 2026 output in line with its updated August plan, with garnet about 20% ahead of plan.
- Ore milled rose 7% from Q2 to 311,122 metric tons.
- Rutile production jumped 74% to 2,190 metric tons; garnet output increased 10% to 11,161 metric tons.
- Hatch ramp-up team onboarded to stabilize plant feed, improve grinding, optimize wet and dry plants to support ramp-up.
- Operations in October saw minor protest-related interruptions; the plant remains operational and producing.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Japanese and South Korean stock markets open

Marvell Technology (MRVL.US) $115 billion "merger of the century" faces lukewarm reception! Stock has dropped over 40%, experts estimate only a 50% chance of completion
Marvell plans to acquire Lamington for 115 billions USD to strengthen its position in AI, but the probability of completion is only 50%. The two stocks have dropped by nearly 40% and about 35% respectively, with Chinese regulatory approval being the biggest uncertainty.
Amid opposition to data centers, Musk doubles down: SpaceX (SPCX.US) plans to build a $24 billion computing center and gas power plant in Texas.
According to a public hearing notice published on the Starbase website, SpaceX plans to build, own, and operate a gas-fired power plant and a supercomputing facility at its company town in Starbase, Texas.