Black Hills signs agreements to supply power for planned Google data center in Wyoming
Bitget2026/10/06 20:10Black Hills signed definitive agreements to serve Google’s planned Cheyenne, Wyoming data center through 2048, effective Sept. 30, 2026. Up to 590 MW of grid-connected service planned, starting late 2027, ramping to peak load in 2030. Plans USD 1.8 billion investment in 564 MW of new natural gas generation; returns begin contributing to earnings in 2027. Will manage about 2.1 GW of third-party contracted resources via a private microgrid; management fees start in late 2027. Project expected to generate about USD 150 million net income in 2030; targets about USD 2.4 billion unlevered free cash flow through 2048. Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Black Hills Corporation published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202610061610PRIMZONEFULLFEED9840884) on October 06, 2026, and is solely responsible for the information contained therein.
- Black Hills signed definitive agreements to serve Google’s planned Cheyenne, Wyoming data center through 2048, effective Sept. 30, 2026.
- Up to 590 MW of grid-connected service planned, starting late 2027, ramping to peak load in 2030.
- Plans USD 1.8 billion investment in 564 MW of new natural gas generation; returns begin contributing to earnings in 2027.
- Will manage about 2.1 GW of third-party contracted resources via a private microgrid; management fees start in late 2027.
- Project expected to generate about USD 150 million net income in 2030; targets about USD 2.4 billion unlevered free cash flow through 2048.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Toyota to Re-import US-made Camry Cars into Japan in Late November

Spot platinum breaks above $1,550 per ounce, up 1.21% intraday

SoftBank Quarterly Preview: Net Interest-Bearing Debt Rises to 10.8 Trillion Yen