Grande Portage posts FAST-41 federal permitting schedule for New Amalga gold project in Alaska
Bitget2026/09/29 08:01- Grande Portage posted a binding FAST-41 federal permitting schedule for its New Amalga Gold Project on the FPISC dashboard.
- New Amalga entered FAST-41 on July 30, 2026, giving the project a coordinated federal review timetable with public milestone tracking.
- U.S. Forest Service leads the federal permitting process; agencies must explain delays, reset deadlines, provide progress updates.
- Project targets a small-footprint underground gold mine about 20 miles north of Juneau in the Tongass National Forest.
- NI 43-101 resource totals 1,438,500 ounces indicated gold, 515,700 ounces inferred; plan calls for direct shipment of ore offsite.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Production Increase Falls Short, Layoffs First! Boeing (BA.US) Cuts 5% of Commercial Airplane Jobs, Delays 737 Monthly Production Target of 47 Aircraft to 2027
Stephanie Pope, head of Boeing's commercial airplanes division, informed employees in an internal memo on Monday that due to obstacles in increasing aircraft production, the division plans to cut 5% of its workforce.
After acquiring SpotHero, Uber (UBER.US) makes its debut in the parking sector with a parking space reservation feature, initially available in 15 U.S. cities
Uber has launched a brand new parking space reservation feature, which marks its first step in the parking sector following its acquisition of the parking app SpotHero earlier this year.
Arbitrum will welcome a new propAMM