E3 Lithium says Phase 2 Clearwater demonstration facility nears completion as Phase 3 ramps up
Bitget2026/09/29 07:15- E3 Lithium outlined progress on its Clearwater lithium brine project in Alberta, with Phase 2 demonstration operations nearing completion.
- Phase 3 will shift to lithium carbonate production, including a commercial-scale DLE column expected to run through 2027.
- Front-end engineering and feasibility work continues, using new demonstration data, with engineering targeted for completion in 2027.
- A licence application was filed for the Clearwater central processing facility, targeting up to 30,000 tonnes per year of battery-grade lithium carbonate.
- Natural Resources Canada backing includes up to $36.5 million of non-repayable funding to support Phase 3 and FEED.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Production Increase Falls Short, Layoffs First! Boeing (BA.US) Cuts 5% of Commercial Airplane Jobs, Delays 737 Monthly Production Target of 47 Aircraft to 2027
Stephanie Pope, head of Boeing's commercial airplanes division, informed employees in an internal memo on Monday that due to obstacles in increasing aircraft production, the division plans to cut 5% of its workforce.
After acquiring SpotHero, Uber (UBER.US) makes its debut in the parking sector with a parking space reservation feature, initially available in 15 U.S. cities
Uber has launched a brand new parking space reservation feature, which marks its first step in the parking sector following its acquisition of the parking app SpotHero earlier this year.
Arbitrum will welcome a new propAMM