Pensana says Longonjo rare earths mine construction tops 30% as financing talks continue
Bitget2026/09/25 06:05- Pensana flagged funding delays at its Longonjo rare earths mine, extending the construction schedule from 2028 to late 2028.
- Construction is over 30% complete; high-cost site work, detailed design, and long-lead procurement were ramped down pending financing.
- Financing talks continued on Cascade’s USD 165 million investment backed by Qatar; USD 15 million has been received.
- Offtake negotiations advanced to underpin planned debt facilities with ABSA and EXIM.
- Accepted a farm-in at the Coola project with ASX-listed Tyranna, targeting USD 2.6 million exploration spend over three years.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Anthropic "accidentally" leaks IPO documents! Plans to raise $69.3 billion, valuation drops from 2 trillion to 1.3 trillion
Anthropic mistakenly published and then withdrew a prospectus for a planned $69.3 billion fundraising, with its valuation dropping from a peak of $2 trillion to between $1.1 trillion and $1.3 trillion.
Subaru Publishes Transcript of First-Half FYE 2027 Financial Results Presentation
Citi: Occidental Petroleum (OXY.US) Q3 cash flow surpasses expectations, accelerated debt repayment cannot hide concerns over Q4 output
Citi published a research report maintaining Occidental Petroleum's "Neutral" rating, with a target price of $65.
WikiLeaks Founder Julian Assange Welcomes Daughter With Terminator Quote