Atlas Energy Solutions unit signs USD 340.5 million balance-of-plant equipment deal with Wyoming Machinery Co
Bitget2026/09/24 21:23- Atlas Energy Solutions unit Shackelford 1 signed a purchase agreement with Wyoming Machinery for balance-of-plant equipment priced at about USD 340.5 million.
- Equipment is scheduled to be available for shipment from June 2027 through December 2027; payments run from September 2026 through May 2027.
- Separately, Shackelford 1 signed a generator purchase agreement with Wyoming Machinery for about 328 MW of generation equipment priced at about USD 273 million.
- Generator equipment is scheduled to be ready to ship from April 2027 through February 2028; payments run from September 2026 through January 2028.
- Generator deal is expected to satisfy part of ProjectCo’s purchase obligation under its previously announced Global Framework Agreement with Caterpillar.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Anthropic "accidentally" leaks IPO documents! Plans to raise $69.3 billion, valuation drops from 2 trillion to 1.3 trillion
Anthropic mistakenly published and then withdrew a prospectus for a planned $69.3 billion fundraising, with its valuation dropping from a peak of $2 trillion to between $1.1 trillion and $1.3 trillion.
Subaru Publishes Transcript of First-Half FYE 2027 Financial Results Presentation
Citi: Occidental Petroleum (OXY.US) Q3 cash flow surpasses expectations, accelerated debt repayment cannot hide concerns over Q4 output
Citi published a research report maintaining Occidental Petroleum's "Neutral" rating, with a target price of $65.
WikiLeaks Founder Julian Assange Welcomes Daughter With Terminator Quote