EcoGraf flags 20% Phase 1 capacity uplift for Epanko graphite project to 87,600 tpa
Bitget2026/09/24 16:15- EcoGraf flagged a value-engineering review for its Epanko graphite project that lifts Phase 1 nominal capacity 20% to 87,600 tpa.
- Estimated C1 costs for the first 10 years fell 5.8% versus the February 2026 BFS to about USD 512.3 per tonne.
- The February 2026 BFS case of 73,000 tpa remains the base for development funding, with the 87,600 tpa case post-FID.
- Preliminary work indicated the 20% uplift needs no change to the BFS layout, with about USD 12 million in incremental capex.
- Higher output could support a single 25,000 tpa HFfree battery anode material plant, backing expansion plans in Europe, Asia, the US.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Anthropic "accidentally" leaks IPO documents! Plans to raise $69.3 billion, valuation drops from 2 trillion to 1.3 trillion
Anthropic mistakenly published and then withdrew a prospectus for a planned $69.3 billion fundraising, with its valuation dropping from a peak of $2 trillion to between $1.1 trillion and $1.3 trillion.
Subaru Publishes Transcript of First-Half FYE 2027 Financial Results Presentation
Citi: Occidental Petroleum (OXY.US) Q3 cash flow surpasses expectations, accelerated debt repayment cannot hide concerns over Q4 output
Citi published a research report maintaining Occidental Petroleum's "Neutral" rating, with a target price of $65.
WikiLeaks Founder Julian Assange Welcomes Daughter With Terminator Quote